Planning: MRP, Forecasting, Scheduling & ATP
Multi-level MRP netting
Planned Orders โ Run MRP Netting explodes pending demand level by level through the BOM. At every level the gross requirement is netted against:
- on-hand stock at the node, and
- scheduled receipts (open production orders for that item).
Only the net shortfall becomes a planned order, with due dates offset one lead time earlier per BOM level. The run report shows gross / on-hand / receipts / net per item per level.
Demand 100 FG (on hand 30) โ net 70 FG planned
โโ needs 140 SUB (on hand 20) โ net 120 SUB planned
โโ needs 360 RAW (on hand 0) โ net 360 RAW planned
The CLI equivalent is php artisan mfg:mrp-net.
Forecasting
Forecast combines a statistical baseline (moving average + trend) with optional AI adjustment, tracks forecast accuracy (MAPE), and feeds demand planning.
APS โ the capacity board
Schedule shows a 14-day board: work centers ร days, cells coloured by load. Two ways to fill it:
- Run โ greedy earliest-due-first packing (fast, predictable).
- Optimize โ simulates several dispatch sequences (earliest-due, shortest-processing, critical-ratio), balances flexible work onto the least-loaded work center and runs a late-order local search; the lowest-cost plan wins. The toast tells you which strategy won.
Drag any order chip to a different day or work center to override the machine โ overloads raise a live alert (and a Momentum work item).
Global ATP
On Inter-Plant Transfers, the Global ATP card answers "can we promise N units of X?" across every plant: on-hand + scheduled receipts โ committed demand, per plant and network-wide, with the earliest promise date.