Getting Started: 最初の生産注文

はじめに:最初の生産注文

空のモジュールから生産注文の完了まで、15分。

1. 工場を設定する(一度だけ)

Step 1  Admin → Manufacturing → Work Centers
        Create one work center per line/cell. Set daily capacity minutes.

Step 2  Admin → Manufacturing → BOMs
        Create a BOM for a product you make: output item + component lines.
        Publish a version (effective from today).

Step 3  (Optional) Routings
        Add operation steps with setup/run times per work center —
        the scheduler uses them; unrouted items still schedule fine.

Step 4  (Optional) Industry preset
        Pick a preset (food, pharma, electronics…) to auto-activate
        the compliance features your industry expects.

2. 日々の運用を開始する

Demand arrives (order, forecast or manual signal)
   ↓
Planned order proposed (MRP)   →  firm it when you agree
   ↓
Production order created       →  release to the floor
   ↓
Issue materials from stock     →  WIP tracked automatically
   ↓
Record output (good/graded/by-products)
   ↓
Quality inspection (if the item's policy requires it)
   ↓
Complete the order             →  finished goods enter inventory,
                                  actual costs post to Accounting

すべてのステップがライブイベントを発火し、dashboardやボードがリアルタイムで更新されるため、全員に最新状況を確認できます。

3. 小規模ショップ向けショートカット

計画工程をすべてスキップして、生産注文 → 新規でBOM、数量、納期を指定します。その他(計画、スケジューリング、予測)は、必要になるまで無効のままにしておけます。